| 2009 |
 |
| December
F??
|
| |
 |
February
- Ground test hours past 2,500
January
- FTB second flight achieves maximum power
|
|
 |
| 2008 |
|
December
November
- FTB low speed taxi trials begin
- Ground testing hours pass 2,000
September
- FTB ground running achieves 100% power
- Delivery of engines for aircraft MSN02 completed
June
- First ground runs of the TP400-D6 engine & Ratier-Figeac propeller installed upon the Marshall-owned C-130 test aircraft.
- Ground testing hours pass 1,500
April
- Successful completion of bird strike & water ingestion tests; attained required 150 hours of cyclic endurance running under loads for the power gearbox.
- Flight Clearance Note for the FTB engine issued.
February
- Flight Test Engines for the first Airbus A400M delivered & installation underway at the final assembly line of the A400M military transport aircraft in Seville.
- Endurance tests successfully completed on ITP indoor test bed located at the Ajalvir plant, close to Madrid (Spain) & on dedicated power rig for the gearbox at the Avio site in Torino (Italy).
|
|
| 2007 |
 |
- First engine to test in Sevilla.
- Delivery of flying test bed engine.
|
|
| 2006 |
 |
|
|
|
| 2005 |
 |
|
|
|
| 2004 |
 |
|
|
|
| 2003 |
 |
|
|
|
| 2002 |
 |
- Creation of Europrop International
|
|